Which Greater Austin cities require a permit for an EV charger, panel upgrade or standby generator, who may do the work, and what two 2025 Texas laws changed.

Every Greater Austin city whose pages answer it requires a permit to replace an electrical panel, and most say the same of a new circuit for an EV charger. A Texas-licensed electrician does most of this work. A homeowner can do it only in some cities, only on the home they own and live in, and in Austin never on the main electric service. Standby generators are where the rules are moving: two Texas laws that took effect on September 1, 2025 changed what cities may require for them.

Each of these upgrades runs through two offices: the city's permit desk and the electric utility, which owns the meter. The table gives each city's short answer, from its own pages, read on November 15, 2026. The sections below give the details.

CityEV chargerPanelGenerator
AustinPermitPermitListed
Round Rock$50 permit$50 permitListed, $150
GeorgetownPermitPermitListed
LakewayPermitPermitAsk
West Lake Hills$75 small project$75 small projectAsk
Lago VistaAskPermitListed

"Ask" means the city's pages don't answer it, so call before the work starts. "Listed" means the city's pages list a generator permit, which a 2025 state law may limit; see Texas law below. Cedar Park, Leander, Pflugerville, Hutto and Bee Cave are covered at the end. These rules apply inside city limits; an address can carry a city's name and still be outside them.

Austin

What needs a permit. Since September 1, 2026, Austin's electrical code, the 2026 National Electrical Code with local amendments, says anyone who will install, alter, repair or replace an electrical system "must apply and obtain a permit before the activity commences." The exemptions are small: swapping a switch, outlet, ceiling fan or light fixture, reinstalling a GFCI or AFCI outlet, replacing a breaker with one of the same rating when the service stays on, and low-voltage work. A new circuit, an EV charger, a panel, a service change and a generator are not on the list. The city's older "work exempt" web page still shows a shorter list; the ordinance is the current rule.

Who can do it. The permit goes to an electrical contractor registered with the city, whose electrician of record holds a Texas master electrician license. The exception is the Homestead Permit: the owner must have a homestead exemption on file, the work must be in their own principal residence, and they must do it themselves. The Homestead Permit doesn't cover the main electric service, so a service or main-panel upgrade needs a licensed contractor.

The meter. For a service rebuild, the contractor schedules a controlled outage with Austin Energy, only Austin Energy crews set and remove meters, and power comes back after the city inspection passes. Austin Energy also charges for a new meter or service wire, $200 for a single-phase meter alone. Homes outside city limits that Austin Energy serves need an Austin electric permit when the work needs an outage or changes service equipment.

EV chargers. Austin Energy pays 50% of the cost of a new Level 2 charger, up to $500, when the charger is on its Power Partner EV list and the customer owns or leases a plug-in vehicle and enrolls in Power Partner EV. You apply online after installation, with the receipt, and the installation must meet code and "permitting requirements," which the rebate page makes the customer's responsibility. Power Partner EV adds a $50 bill credit at enrollment and $25 after a year.

Generators. Austin Energy's safety page says installing a transfer switch "requires an electrical permit" from a registered licensed electrical contractor. Its contractor page lists a few meter-socket transfer devices that need registration and a field consultation instead of a permit. Austin also lists a separate plumbing permit for a gas or propane generator. Under the 2025 state law, a contractor can instead use a third-party review and inspection, and the city then issues the permit within three business days; any job that needs a shutdown still needs a city electrical permit and inspection. In Austin's Wildland-Urban Interface areas, a generator needs a spark arrestor.

Round Rock

Round Rock puts electrical work on a standalone trade permit for homeowners and contractors, at $50, with a plan review that usually takes 3 to 5 business days. An electrical upgrade or replacement needs a torque letter signed by the master electrician, with their license number. Round Rock runs a one-permit system, so every contractor on the job must be on the permit before it's issued.

Round Rock lists a $150 permit for a standby generator, which covers the electrical and the gas line in one application. It needs a one-line diagram from the generator to the transfer switch and panel, the equipment's clearances, the fuel type, and gas pipe sizing from the meter to the unit. Review usually takes 3 to 5 business days.

Contractors can instead use the city's SB 1202 checklist for third-party review and inspection. Under that path the permit fee is $100, which doesn't include review or inspection, work can't start until the city issues approval, and the permit closes when a qualified third-party inspector submits the report. Building Inspection: 512-218-5550.

Georgetown

Georgetown requires an electric permit to add or move an outlet, to work on the weatherhead or meter can, and to replace a service panel or an electric meter. The exemptions follow the model building code's list: temporary plug-in lighting, reinstalling outlets, a same-capacity breaker swap, very low-voltage wiring and minor repairs such as lamps. A trade permit costs $50 plus a $10 technology fee. Georgetown will disconnect and reconnect power without a permit for only two jobs: painting the house and changing out a main breaker (512-930-3640).

An owner who isn't licensed can get a homestead permit for plumbing, electrical or mechanical work on the home they own and live in, after filing a notarized affidavit with proof of the homestead exemption from the Williamson County appraisal district. Nobody else may do work under that permit.

Georgetown lists a Generator Permit for a standby generator, with the electrical and plumbing permits under it; a service rebuild adds a second electric permit. Inspectors check, among other things, that the generator sits at least 5 feet from any opening in an exterior wall and on a pad at least 3 inches above grade. Georgetown warns that a generator permit doesn't exempt the unit from the city's noise rules. Its page notes both 2025 state laws and says the city is updating its process for them.

Lakeway, West Lake Hills and Lago Vista

Lakeway requires a permit for a new electrical service, service upgrades or relocations, and "installation of electric wiring and equipment." An owner may make minor repairs without a permit only when the ordinance doesn't regulate them, and should call Building and Development Services at 512-314-7540 to ask first. Applications must show the project went to the subdivision's architectural control board, where there is one.

West Lake Hills puts electrical work on its Small Project Application. A small project permit costs $75, plus the $5 technology fee on every permit, and applications go through MGO Connect only. A general contractor on a project worth $25,000 or more must register with the city.

Lago Vista handles a panel replacement on its Small Jobs permit; the application states the panel size and whether it's like for like, and a final inspection is usually the only one. Its pages list a separate generator permit, with a site plan, electrical plans and a gas pipe diagram from the responsible master plumber, then permanent-power, gas-test and final inspections. Contractors must register with the city each year. Permitting: 512-267-1155.

Texas law and your utility

Homeowners and licenses. Texas doesn't require a license for electrical work on a home the person owns and lives in, but the state notes that city rules may override that exemption, which is why each city's homeowner rule above matters.

The 2025 generator laws. Since September 1, 2025, SB 1202 lets a qualified third party, such as a master electrician, review and inspect a home backup power installation of up to 600 volts, and the city must issue its permit within three business days of their approval. SB 1252 bars cities from regulating the installation or inspection of a home backup system that supplies up to 50 kilowatts or stores up to 100 kilowatt-hours, while letting a city-owned utility, such as Austin Energy or Georgetown's, set rules in its own service area. The city pages above still list generator permits, so ask your city and your utility how both laws apply to your project.

PEC. Pedernales Electric Cooperative requires a UL-listed transfer switch, a standby disconnect that PEC can see and reach, and no power sent back onto its lines. Call PEC at 888-554-4732 if the job needs a service change or a meter disconnect.

Other cities nearby

We couldn't confirm these cities' current electrical permit rules on their own pages on November 15, 2026. Call before the work starts: Cedar Park at 512-401-5100, Leander at 512-528-2733 and Pflugerville at 512-990-6300, or the permit offices of Hutto and Bee Cave.

Before the work starts

  1. Find your utility. Austin Energy, Georgetown, Oncor or PEC decides who pulls the meter and when power comes back.
  2. Ask for a load calculation. A Level 2 charger or a generator adds a big load, and the calculation shows whether the panel can carry it.
  3. Check the license. Look up the electrician on the Texas Department of Licensing and Regulation's license search before you sign.
  4. Write the permit into the contract. Say who applies, who pays and who schedules each inspection, and make sure the permit is closed after the final one.

This guide is practical information, not a permit decision. Each city decides for a specific address and project.

Where Completa fits

Tell Completa once what you're adding: where the charger goes and how far that is from the panel, the panel's size and age, or the generator's size and fuel. You see your estimate before anyone comes out, then pick a local pro and agree in writing who handles any permit and the utility's part before work starts. When the job is done, it's saved to your home's record.

Frequently asked questions

Do I need a permit to install an EV charger in Austin?

Yes. Since September 1, 2026, Austin's electrical code requires a permit before anyone installs or alters an electrical system, and no exemption covers a new circuit or a charger. A registered, Texas-licensed electrical contractor gets it, or a homeowner who qualifies for a Homestead Permit on their own principal residence.

Can I replace my own electrical panel in Greater Austin?

Not in Austin, where the Homestead Permit excludes the main electric service. Georgetown issues a homestead permit to an owner who files a notarized affidavit that the home is their homestead, and that owner must do the work personally. Where an owner may do the work, the permit and inspection still apply, and the utility handles the meter.

Do I need a permit for a whole-house standby generator?

Austin, Round Rock, Georgetown and Lago Vista list one on their pages, with a plumbing permit or gas test for a gas unit. But since September 1, 2025, a Texas law, SB 1252, has barred cities from regulating the installation or inspection of a home backup system of up to 50 kilowatts, while a city-owned utility such as Austin Energy can still set rules in its own area. Ask your city and your utility what applies before the work starts.

Does Austin Energy give a rebate for a home EV charger?

Yes: 50% of the cost, up to $500, for an eligible Level 2 charger, if you're an Austin Energy customer who owns or leases a plug-in vehicle and enrolls in Power Partner EV. The installation must meet permitting requirements, and you apply after it's installed.